FOLLOW THE SPORTS PAVILION BUILDING PROGRESS

The final day
24th March, Almost Gone
We just can't believe it
but it was cleared in the day
Ready for a start on
2nd April
12th April Building in progress
18th April Almost ready for facing bricks
The West Wing and drainage work
26th April keeping the damp out
They'll be ready for night
Ready for the big push 4th May
Steve will soon need scaffolding
View across the West Wing 9th May
Beginning to look like a pavilion 17th May
A view from the back 24th May
Almost ready for roof 11th June
The North wing taking shape 18th June
23rd June - looking good
Almost ready for felting 27th June
Hoping to beat the rain 2nd
July
Tiling 9th July
View from the back 12th July
The
scorer's view
23rd July
Building up the internal walls in North Wing
The scaffolding comes down 6th August
Further developments inside 8th August
Steve & John concreting changing rooms
11th October
Preparing shower trays 15th Oct
Shower 30th Oct
Part of Lounge Area 30th Oct
Up to the Scorebox 30th Oct
Chairman John Crossland painting the lounge 8th Dec
Don't get in his way
Project Manager Steve Milner filling in the gaps 8th Dec
They have been busy 10th Dec
Kitchen takes shape -
4th January
Rod laying floor covering 29th Jan
A peek into the showers and toilet area 12th Feb
Officials changing room
East Entrance
Changing area 17th Feb
Officials changing room 17th Feb
Almost ready to take scaffolding down
Kitchen 17th Feb
Rod fitting Lounge carpet 20th Feb
Vic puts finishing touches to
benches
Pete completes the job with varnish
Lounge fully carpeted 21st Feb
Entrance with kitchen hatch through double doors
Stairs leading to score-box
John & Vic laying pinkerbs being overlooked by project manager
Bass preparing base for footpath 27th Feb
Block paving - 2nd March
The last straight
AT LAST -
No fencing
The completed pavilion
John & Steve having a cuppa from Emma & Holly
John & Vic line up pinkerbs in the car park
Pinkerbing the road with Bass supervising